WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

AURUS

Project Status as on Quarter ending 31-12-2020
Updated as on 02-03-2021

Booking Status

  • Residential Apartments Booked
    100

  • Basement Parking Booked
    51

  • Covered Car Parking Booked
    32

  • Mechanical Parking Booked
    54

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK 1 33 Under Construction
BLOCK 2 34 Under Construction
BLOCK 1 1 Under Construction
BLOCK 1 2 Under Construction
BLOCK 1 3 Under Construction
BLOCK 1 4 Under Construction
BLOCK 1 5 Under Construction
BLOCK 1 6 Under Construction
BLOCK 1 7 Under Construction
BLOCK 1 8 Under Construction
BLOCK 1 9 Under Construction
BLOCK 1 10 Under Construction
BLOCK 1 11 Under Construction
BLOCK 1 12 Under Construction
BLOCK 1 13 Under Construction
BLOCK 1 14 Under Construction
BLOCK 1 15 Under Construction
BLOCK 1 16 Under Construction
BLOCK 1 17 Under Construction
BLOCK 1 18 Under Construction
BLOCK 1 19 Under Construction
BLOCK 1 20 Under Construction
BLOCK 1 21 Under Construction
BLOCK 1 22 Under Construction
BLOCK 1 23 Under Construction
BLOCK 1 24 Under Construction
BLOCK 1 25 Under Construction
BLOCK 1 26 Under Construction
BLOCK 1 27 Under Construction
BLOCK 1 28 Under Construction
BLOCK 1 29 Under Construction
BLOCK 1 30 Under Construction
BLOCK 1 31 Under Construction
BLOCK 1 32 Under Construction
BLOCK 1 33 Under Construction
BLOCK 2 1 Under Construction
BLOCK 2 2 Under Construction
BLOCK 2 3 Under Construction
BLOCK 2 5 Under Construction
BLOCK 2 6 Under Construction
BLOCK 2 7 Under Construction
BLOCK 2 8 Under Construction
BLOCK 2 9 Under Construction
BLOCK 2 10 Under Construction
BLOCK 2 11 Under Construction
BLOCK 2 12 Under Construction
BLOCK 2 13 Under Construction
BLOCK 2 14 Under Construction
BLOCK 2 15 Under Construction
BLOCK 2 16 Under Construction
BLOCK 2 17 Under Construction
BLOCK 2 30 Under Construction
BLOCK 2 31 Under Construction
BLOCK 2 32 Under Construction
BLOCK 2 34 Under Construction
BLOCK 1 29 Under Construction
BLOCK 1 32 Under Construction
BLOCK 2 18 Under Construction
BLOCK 2 19 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 BLOCK 1 & 2
2 LANDSCAPE-TOWER-1
3 LANDSCAPE-TOWER 2
4 ENTRANCE LOBBY
5 LANDSCAPE-TOWER-2
6 LANDSCAPE-TOWER-1

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction BLOCK 1 & 2
2 Under Construction CLUB HOUSE 1ST FLOOR TOWER-1
3 Under Construction CLUB HOUSE GROUND FLOOR-TOWER-1
4 Under Construction FIRE REFUGE PLATFORM-TOWER 1
5 Under Construction GROUND FLOOR PARKING
6 Under Construction ROOF TOWER-1
7 Under Construction LMR STAIR TOWER-1
8 Under Construction MAIN STAIR TOWER-1
9 Under Construction FIRE REFUGE PLATFORM TOWER-2
10 Under Construction STAIR TOWER-2
11 Under Construction INDOOR GAMES ROOM- CLUB HOUSE
12 Under Construction SWIMMING POOL
13 Under Construction FIRST FLOOR CLUB HOUSE JACUZZI
14 Under Construction BASEMENT FIRE CONTROL
15 Under Construction BASEMENT WATER TREATMENT PLANT

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download