Project Status as on Quarter ending 30-09-2024
Updated as on 01-10-2024

Booking Status

  • Residential Apartments Booked
    24

  • Basement Parking Booked
    12

  • Covered Car Parking Booked
    9

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
WING 1 - FIRST TO 8TH FLOOR - RESIDENTIAL 1 Under Construction
WING 1 - FIRST TO 8TH FLOOR - RESIDENTIAL 2 Not Started
WING 1 - FIRST TO 8TH FLOOR - RESIDENTIAL 3 Not Started
WING 1 - FIRST TO 8TH FLOOR - RESIDENTIAL 4 Not Started
WING 1 - FIRST TO 8TH FLOOR - RESIDENTIAL 5 Not Started
WING 1 - FIRST TO 8TH FLOOR - RESIDENTIAL 6 Not Started
WING 1 - FIRST TO 8TH FLOOR - RESIDENTIAL 7 Not Started
WING 1 - FIRST TO 8TH FLOOR - RESIDENTIAL 8 Not Started
WING 2 - FIRST TO 8TH FLOOR - RESIDENTIAL 1 Under Construction
WING 2 - FIRST TO 8TH FLOOR - RESIDENTIAL 2 Not Started
WING 2 - FIRST TO 8TH FLOOR - RESIDENTIAL 3 Not Started
WING 2 - FIRST TO 8TH FLOOR - RESIDENTIAL 4 Not Started
WING 2 - FIRST TO 8TH FLOOR - RESIDENTIAL 5 Not Started
WING 2 - FIRST TO 8TH FLOOR - RESIDENTIAL 6 Not Started
WING 2 - FIRST TO 8TH FLOOR - RESIDENTIAL 7 Not Started
WING 2 - FIRST TO 8TH FLOOR - RESIDENTIAL 8 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Under Construction Stairs
3 Not Started Lift
4 Not Started Roof

Approval for NOC