Booking Status

  • Residential Apartments Booked
    130

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    35

  • Mechanical Parking Booked
    60

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 5 Under Construction
1 6 Under Construction
1 7 Under Construction
1 8 Under Construction
1 9 Under Construction
1 10 Under Construction
1 11 Under Construction
1 12 Under Construction
2 1 Under Construction
2 2 Under Construction
2 3 Under Construction
2 4 Under Construction
2 5 Under Construction
2 6 Under Construction
2 7 Under Construction
2 8 Under Construction
2 9 Under Construction
2 10 Under Construction
2 11 Under Construction
2 12 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure - Block 1
2 Internal Infrastructure - Block 2

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction STP
2 Under Construction Community Hall
3 Under Construction Swimming Pool

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download