Booking Status

  • Residential Apartments Booked
    4

  • Commercial Unit Booked
    3

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    3

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Not Started
1 2 Not Started
1 3 Not Started
1 4 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 FIRE EXTINGUISHER FACILITIES
2 EMERGENCY EVACUATION
3 WATER FACILITY

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started POWER BACKUP
2 Not Started STAIRS
3 Not Started LIFT
4 Not Started LOBBY
5 Not Started ROOF
6 Not Started SEPTIC TANK
7 Under Construction UNDER-GROUND WATER RESERVOIR
8 Not Started OVERHEAD TANK

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download