WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

ARIA RABINDRA

Project Status as on Quarter ending 30-06-2019
Updated as on 31-07-2019

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK-4 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 PHOTO

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction COMMON AREA PHOTO

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download