New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

ALTITUDE 16

Project Status as on Quarter ending 31-12-2025
Updated as on 09-01-2026

Booking Status

  • Residential Apartments Booked
    18

  • Basement Parking Booked
    15

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    8

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 10 Completed Without CC
1 11 Completed Without CC
1 12 Completed Without CC
1 13 Completed Without CC
1 14 Completed Without CC
1 15 Completed Without CC
1 16 Completed Without CC
1 17 Completed Without CC
1 18 Completed Without CC
1 19 Completed Without CC
1 20 Completed Without CC
1 21 Completed Without CC
1 22 Under Construction
1 23 Under Construction
1 1 Under Construction
1 2 Completed Without CC
1 3 Completed Without CC
1 4 Completed Without CC
1 5 Completed Without CC
1 6 Completed Without CC
1 7 Completed Without CC
1 8 Completed Without CC
1 9 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Emergency Evacuation
2 Water Facility
3 Fire Fighting Systems

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Roof
2 Completed Without CC Gym
3 Under Construction Temple
4 Under Construction Game Room
5 Under Construction Swimming Pool
6 Under Construction Podium
7 Under Construction Community Hall
8 Completed Without CC Stairs
9 Completed Without CC Lift
10 Under Construction Under Ground Water Reservoir
11 Completed Without CC Overhead Tank
12 Completed Without CC Lobby

Approval for NOC