Booking Status

  • Residential Apartments Booked
    25

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    16

  • Mechanical Parking Booked
    8

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1ST to 4th Floor- Residential 1 Completed Without CC
1ST to 4th Floor- Residential 2 Completed Without CC
1ST to 4th Floor- Residential 3 Completed Without CC
1ST to 4th Floor- Residential 4 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facilty
4 Use of Renewable Energy

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Car Parking
2 Completed Without CC DG
3 Completed Without CC Main Gate
4 Completed Without CC Lobby
5 Completed Without CC Stairs
6 Completed Without CC Lift
7 Completed Without CC Terrace

Approval for NOC