WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

TILOTTAMA NATURAL CITY PHASE I

Project Status as on Quarter ending 30-09-2024
Updated as on 22-11-2024

Booking Status

  • Residential Apartments Booked
    44

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
2 1 Under Construction
2 2 Under Construction
2 3 Under Construction
2 4 Under Construction
3 1 Under Construction
3 2 Under Construction
3 3 Under Construction
3 4 Under Construction
4 1 Under Construction
4 2 Under Construction
4 3 Under Construction
4 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Extinguisher Facilities
2 Water Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lift
2 Under Construction Lobby
3 Under Construction Stairs
4 Under Construction Roof
5 Under Construction Overhead Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download