New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Visaaya

Project Status as on Quarter ending 30-09-2025
Updated as on 06-10-2025

Booking Status

  • Residential Apartments Booked
    19

  • Basement Parking Booked
    22

  • Covered Car Parking Booked
    26

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK - B+ G + 19th Floor- Residential 1 Under Construction
BLOCK - B+ G + 19th Floor- Residential 2 Not Started
BLOCK - B+ G + 19th Floor- Residential 3 Not Started
BLOCK - B+ G + 19th Floor- Residential 4 Not Started
BLOCK - B+ G + 19th Floor- Residential 5 Not Started
BLOCK - B+ G + 19th Floor- Residential 6 Not Started
BLOCK - B+ G + 19th Floor- Residential 7 Not Started
BLOCK - B+ G + 19th Floor- Residential 8 Not Started
BLOCK - B+ G + 19th Floor- Residential 9 Not Started
BLOCK - B+ G + 19th Floor- Residential 10 Not Started
BLOCK - B+ G + 19th Floor- Residential 11 Not Started
BLOCK - B+ G + 19th Floor- Residential 12 Not Started
BLOCK - B+ G + 19th Floor- Residential 13 Not Started
BLOCK - B+ G + 19th Floor- Residential 14 Not Started
BLOCK - B+ G + 19th Floor- Residential 15 Not Started
BLOCK - B+ G + 19th Floor- Residential 16 Not Started
BLOCK - B+ G + 19th Floor- Residential 17 Not Started
BLOCK - B+ G + 19th Floor- Residential 18 Not Started
BLOCK - B+ G + 19th Floor- Residential 19 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facilty
4 Use of Renewable Energy

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Lobby
2 Not Started Stairs
3 Not Started Lift
4 Not Started Roof

Approval for NOC