New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

Sonarbhoomi

Project Status as on Quarter ending 31-12-2022
Updated as on 24-04-2025

Booking Status

  • Residential Apartments Booked
    67

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    30

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed With CC
2 1 Completed With CC
1 1 Completed With CC
2 1 Completed With CC
1 1 Completed With CC
1 2 Completed With CC
1 3 Completed With CC
1 4 Completed With CC
2 1 Completed With CC
2 2 Completed With CC
2 3 Completed With CC
2 4 Completed With CC
2 4 Completed With CC
1 4 Completed With CC
1 1 Completed With CC
1 2 Completed With CC
1 3 Completed With CC
2 1 Completed With CC
1 1 Completed With CC
1 1 Completed With CC
2 1 Completed With CC
1 1 Completed With CC
1 1 Completed With CC
1 3 Completed With CC
1 2 Completed With CC
1 4 Completed With CC
2 1 Completed With CC
1 4 Completed With CC
1 1 Completed With CC
1 1 Completed With CC
1 4 Completed With CC
1 3 Completed With CC
1 2 Completed With CC
2 1 Completed With CC
2 4 Completed With CC
2 1 Completed With CC
1 1 Completed With CC
1 2 Completed With CC
2 1 Completed With CC
1 1 Completed With CC
1 2 Completed With CC
1 3 Completed With CC
1 4 Completed With CC
2 1 Completed With CC
2 3 Completed With CC
2 4 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drainage and Electrical Works
2 Construction Progress
3 Elevation and common areas
4 Update
5 Driveway Works
6 COmmunity hall
7 Club
8 Boundary wall
9 Summary of construction status
10 lift
11 community hall
12 tank
13 common corridor
14 covering letters
15 Corridoor
16 Roads
17 Swimming pool
18 Summary
19 Road
20 swimming pool
21 driweway
22 lake area
23 parking area
24 Covering letter for updates
25 DRIVEWAY WORKS
26 SWIMMING POOL WORKS
27 COMMUNITY HALL WORKS
28 COMMON WORKS
29 BLOCK 2 CONSTRUCTION PROGRESS
30 BLOCK 1 CONSTRUCTION PROGRESS
31 COVERING LETTER FOR PROGRESS OF CONSTRUCTION
32 COVERING LETTER FOR NOC AND APPROVALS
33 SUMMRY OF ALL WORKS AND NOC

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Gate, Swimming pool, Gym, Community Hall
2 Completed With CC Construction Progress
3 Completed With CC Covering Letter for Quater Updates
4 Completed With CC hira update document
5 Completed With CC hira pics
6 Completed With CC Driveway
7 Completed With CC Community hall
8 Completed With CC Gym
9 Completed With CC Summary of construction status
10 Completed With CC Quaterly update covering letter and annexures
11 Completed With CC swimming pool
12 Completed With CC main gate
13 Completed With CC elevation
14 Completed With CC community hall
15 Completed With CC tank
16 Completed With CC main gate
17 Completed With CC Covering Letters
18 Completed Without CC Road
19 Completed With CC Swimming Pool
20 Completed With CC Playground
21 Completed With CC Open Terrace
22 Completed With CC Deck Lighting
23 Completed With CC Summary
24 Completed With CC lake area
25 Completed With CC driweway
26 Completed With CC swimming pool
27 Completed With CC covering letter
28 Completed With CC COMMON AREA WORKS
29 Completed With CC DRIVEWAY WORKS
30 Completed With CC COMMUNITY HALL
31 Completed With CC SWIMMING POOL WORKS
32 Completed With CC COVERING LETTER FOR ANY MODIFICATIONS
33 Completed With CC COVERING LETTER FOR UNITS BOOKED
34 Completed With CC COVERING LETTER FOR QUARTERLY UPDATES ON 30/06/19
35 Completed With CC SUMMARY OF ALL WORKS

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Such other approvals as may be required and obtained for the project 08-12-2021 08-04-2021 22-02-2021 Completion Certificate for Block 1