New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

GULMOHAR PHASE II

Project Status as on Quarter ending 31-12-2025
Updated as on 10-01-2026

Booking Status

  • Residential Apartments Booked
    6

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    6

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
D1 1 Not Started
D1 2 Not Started
D2 1 Not Started
D2 2 Not Started
D3 1 Not Started
D3 2 Not Started
D4 1 Not Started
D4 2 Not Started
D5 1 Not Started
D5 2 Not Started
D6 1 Not Started
D6 2 Not Started
D7 1 Not Started
D7 2 Not Started
D8 1 Not Started
D8 2 Not Started
D9 1 Under Construction
D9 2 Under Construction
D10 1 Under Construction
D10 2 Under Construction
D11 1 Under Construction
D11 2 Under Construction
D12 1 Under Construction
D12 2 Under Construction
D13 1 Under Construction
D13 2 Under Construction
D14 1 Under Construction
D14 2 Under Construction
D15 1 Under Construction
D15 2 Under Construction
D16 1 Under Construction
D16 2 Under Construction
D17 1 Under Construction
D17 2 Under Construction
D18 1 Under Construction
D18 2 Under Construction
D19 1 Under Construction
D19 2 Under Construction
D20 1 Under Construction
D20 2 Under Construction
E1 1 Under Construction
E1 2 Under Construction
E2 1 Under Construction
E2 2 Under Construction
E3 1 Under Construction
E3 2 Under Construction
E4 1 Under Construction
E4 2 Under Construction
E5 1 Under Construction
E5 2 Under Construction
E6 1 Under Construction
E6 2 Under Construction
E7 1 Under Construction
E7 2 Under Construction
E8 1 Under Construction
E8 2 Under Construction
E9 1 Under Construction
E9 2 Under Construction
E10 1 Under Construction
E10 2 Under Construction
E11 1 Under Construction
E11 2 Under Construction
E12 1 Under Construction
E12 2 Under Construction
E13 1 Under Construction
E13 2 Under Construction
E14 1 Under Construction
E14 2 Under Construction
E15 1 Under Construction
E15 2 Under Construction
E16 1 Under Construction
E16 2 Under Construction
E17 1 Under Construction
E17 2 Under Construction
E18 1 Under Construction
E18 2 Under Construction
E19 1 Under Construction
E19 2 Under Construction
F1 1 Under Construction
F1 2 Under Construction
F2 1 Under Construction
F2 2 Under Construction
F3 1 Under Construction
F3 2 Under Construction
F4 1 Under Construction
F4 2 Under Construction
F5 1 Under Construction
F5 2 Under Construction
F6 1 Under Construction
F6 2 Under Construction
F7 1 Under Construction
F7 2 Under Construction
F8 1 Under Construction
F8 2 Under Construction
F9 1 Under Construction
F9 2 Under Construction
F10 1 Under Construction
F10 2 Under Construction
F11 1 Under Construction
F11 2 Under Construction
F12 1 Under Construction
F12 2 Under Construction
F13 1 Under Construction
F13 2 Under Construction
F14 1 Under Construction
F14 2 Under Construction
F15 1 Under Construction
F15 2 Under Construction
F16 1 Under Construction
F16 2 Under Construction
F17 1 Under Construction
F17 2 Under Construction
F18 1 Under Construction
F18 2 Under Construction
G1 1 Under Construction
G1 2 Under Construction
G2 1 Under Construction
G2 2 Under Construction
G3 1 Under Construction
G3 2 Under Construction
G4 1 Under Construction
G4 2 Under Construction
G5 1 Under Construction
G5 2 Under Construction
G6 1 Under Construction
G6 2 Under Construction
G7 1 Under Construction
G7 2 Under Construction
G8 1 Under Construction
G8 2 Under Construction
G9 1 Under Construction
G9 2 Under Construction
G10 1 Under Construction
G10 2 Under Construction
G11 1 Under Construction
G11 2 Under Construction
G12 1 Under Construction
G12 2 Under Construction
G13 1 Under Construction
G13 2 Under Construction
G14 1 Under Construction
G14 2 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Use of Renewable Energy
2 Drinking Water Facility
3 Emergency Evacuation Services
4 Fire Fighting Facilty

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Lobby
2 Under Construction Entrance
3 Under Construction Stairs
4 Not Started Lift
5 Under Construction Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download