New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

KEVENTER ONE

Project Status as on Quarter ending 31-12-2025
Updated as on 05-01-2026

Booking Status

  • Commercial Unit Booked
    118

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    154

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
South 17 Not Started
South 18 Not Started
South 19 Not Started
South 20 Not Started
South 21 Not Started
South 22 Not Started
South 23 Not Started
South 24 Not Started
South 25 Not Started
South 26 Not Started
South 27 Not Started
South 28 Not Started
South 29 Not Started
South 30 Not Started
South 31 Not Started
South 32 Not Started
South 33 Not Started
South 34 Not Started
South 35 Not Started
South 36 Not Started
South 37 Not Started
South 38 Not Started
South 39 Not Started
NIL 1 Not Started
NIL 2 Not Started
NIL 3 Not Started
NIL 4 Not Started
NIL 5 Not Started
NIL 6 Not Started
NIL 7 Not Started
NIL 8 Not Started
NIL 9 Not Started
NIL 10 Not Started
North 11 Not Started
North 12 Not Started
North 13 Not Started
North 14 Not Started
North 15 Not Started
North 16 Not Started
North 17 Not Started
North 18 Not Started
North 19 Not Started
North 20 Not Started
North 21 Not Started
North 22 Not Started
North 23 Not Started
North 24 Not Started
North 25 Not Started
North 26 Not Started
North 27 Not Started
North 28 Not Started
North 29 Not Started
North 30 Not Started
North 31 Not Started
North 32 Not Started
North 33 Not Started
North 34 Not Started
North 35 Not Started
North 36 Not Started
North 37 Not Started
North 38 Not Started
North 39 Not Started
South 11 Not Started
South 12 Not Started
South 13 Not Started
South 14 Not Started
South 15 Not Started
South 16 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Halipad
2 Fire Fighting Facility
3 Emegency Evacuation Facilities
4 Water Facility
5 Renewable Energy

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Septic Tank
2 Under Construction Piling & Other Initial Work
3 Not Started Stairs
4 Not Started Lift
5 Not Started Lobby
6 Not Started Under Ground Water Reservoir
7 Not Started Overhead Tank
8 Not Started Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download