New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

7 CONVENT

Project Status as on Quarter ending 31-12-2025
Updated as on 09-01-2026

Booking Status

  • Residential Apartments Booked
    93

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    147

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 5 Under Construction
1 6 Under Construction
1 7 Under Construction
1 8 Under Construction
1 9 Under Construction
1 10 Under Construction
1 11 Under Construction
1 12 Under Construction
1 13 Under Construction
1 14 Under Construction
1 15 Under Construction
1 16 Under Construction
1 17 Under Construction
1 18 Under Construction
1 19 Under Construction
1 20 Under Construction
1 21 Under Construction
1 22 Under Construction
1 23 Under Construction
1 24 Under Construction
1 25 Under Construction
1 26 Under Construction
1 27 Under Construction
1 28 Under Construction
1 29 Under Construction
1 30 Under Construction
1 31 Under Construction
1 32 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities
2 Emergency Evacuations
3 Water Facilities

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Stairs
2 Under Construction Lift
3 Under Construction Lobby
4 Under Construction Roof
5 Not Started Under Ground Water Reservoir
6 Not Started Septic Tank
7 Not Started Overhead Tank

Approval for NOC