New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Cellesta Phase II

Project Status as on Quarter ending 30-09-2025
Updated as on 01-11-2025

Booking Status

  • Residential Apartments Booked
    165

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    70

  • Mechanical Parking Booked
    56

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 1 -4TH TO 31ST FLOOR 4 Under Construction
Tower 1 -4TH TO 31ST FLOOR 5 Not Started
Tower 1 -4TH TO 31ST FLOOR 6 Not Started
Tower 1 -4TH TO 31ST FLOOR 7 Not Started
Tower 1 -4TH TO 31ST FLOOR 8 Not Started
Tower 1 -4TH TO 31ST FLOOR 9 Not Started
Tower 1 -4TH TO 31ST FLOOR 10 Not Started
Tower 1 -4TH TO 31ST FLOOR 11 Not Started
Tower 1 -4TH TO 31ST FLOOR 12 Not Started
Tower 1 -4TH TO 31ST FLOOR 13 Not Started
Tower 1 -4TH TO 31ST FLOOR 14 Not Started
Tower 1 -4TH TO 31ST FLOOR 15 Not Started
Tower 1 -4TH TO 31ST FLOOR 16 Not Started
Tower 1 -4TH TO 31ST FLOOR 17 Not Started
Tower 1 -4TH TO 31ST FLOOR 18 Not Started
Tower 1 -4TH TO 31ST FLOOR 19 Not Started
Tower 1 -4TH TO 31ST FLOOR 20 Not Started
Tower 1 -4TH TO 31ST FLOOR 21 Not Started
Tower 1 -4TH TO 31ST FLOOR 22 Not Started
Tower 1 -4TH TO 31ST FLOOR 23 Not Started
Tower 1 -4TH TO 31ST FLOOR 24 Not Started
Tower 1 -4TH TO 31ST FLOOR 25 Not Started
Tower 1 -4TH TO 31ST FLOOR 26 Not Started
Tower 1 -4TH TO 31ST FLOOR 27 Not Started
Tower 1 -4TH TO 31ST FLOOR 28 Not Started
Tower 1 -4TH TO 31ST FLOOR 29 Not Started
Tower 1 -4TH TO 31ST FLOOR 30 Not Started
Tower 1 -4TH TO 31ST FLOOR 31 Not Started
TOWER 2 -2ND& 3RD FLOOR 1 Not Started
TOWER 2 -2ND& 3RD FLOOR 2 Not Started
TOWER 2 -2ND& 3RD FLOOR 3 Not Started
TOWER 2- 4TH TO 31ST Floor 4 Not Started
TOWER 2- 4TH TO 31ST Floor 5 Not Started
TOWER 2- 4TH TO 31ST Floor 6 Not Started
TOWER 2- 4TH TO 31ST Floor 7 Not Started
TOWER 2- 4TH TO 31ST Floor 8 Not Started
TOWER 2- 4TH TO 31ST Floor 9 Not Started
TOWER 2- 4TH TO 31ST Floor 10 Not Started
TOWER 2- 4TH TO 31ST Floor 11 Not Started
TOWER 2- 4TH TO 31ST Floor 12 Not Started
TOWER 2- 4TH TO 31ST Floor 13 Not Started
TOWER 2- 4TH TO 31ST Floor 14 Not Started
TOWER 2- 4TH TO 31ST Floor 15 Not Started
TOWER 2- 4TH TO 31ST Floor 16 Not Started
TOWER 2- 4TH TO 31ST Floor 17 Not Started
TOWER 2- 4TH TO 31ST Floor 18 Not Started
TOWER 2- 4TH TO 31ST Floor 19 Not Started
TOWER 2- 4TH TO 31ST Floor 20 Not Started
TOWER 2- 4TH TO 31ST Floor 21 Not Started
TOWER 2- 4TH TO 31ST Floor 22 Not Started
TOWER 2- 4TH TO 31ST Floor 23 Not Started
TOWER 2- 4TH TO 31ST Floor 24 Not Started
TOWER 2- 4TH TO 31ST Floor 25 Not Started
TOWER 2- 4TH TO 31ST Floor 26 Not Started
TOWER 2- 4TH TO 31ST Floor 27 Not Started
TOWER 2- 4TH TO 31ST Floor 28 Not Started
TOWER 2- 4TH TO 31ST Floor 29 Not Started
TOWER 2- 4TH TO 31ST Floor 30 Not Started
TOWER 2- 4TH TO 31ST Floor 31 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facilty
4 Use of Renewable Energy

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Entry Gate
2 Not Started Lobby
3 Not Started Stairs
4 Not Started Lift
5 Not Started Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download