New Please be informed that the last date for Quarterly Update of Registered Projects has been extended as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

ECOS

Project Status as on Quarter ending 30-09-2022
Updated as on 27-01-2025

Booking Status

  • Residential Apartments Booked
    209

  • Basement Parking Booked
    129

  • Covered Car Parking Booked
    73

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 1 Completed With CC
Block 1 2 Completed With CC
Block 1 3 Completed With CC
Block 1 4 Completed With CC
Block 1 5 Completed With CC
Block 1 6 Completed With CC
Block 1 7 Completed With CC
Block 1 8 Completed With CC
Block 1 9 Completed With CC
Block 1 10 Completed With CC
Block 1 11 Completed With CC
Block 1 12 Completed With CC
Block 2 1 Completed With CC
Block 2 2 Completed With CC
Block 2 3 Completed With CC
Block 2 4 Completed With CC
Block 2 5 Completed With CC
Block 2 6 Completed With CC
Block 2 7 Completed With CC
Block 2 8 Completed With CC
Block 2 9 Completed With CC
Block 2 10 Completed With CC
Block 2 11 Completed With CC
Block 2 12 Completed With CC
Block 3 1 Completed With CC
Block 3 2 Completed With CC
Block 3 3 Completed With CC
Block 3 4 Completed With CC
Block 3 5 Completed With CC
Block 3 6 Completed With CC
Block 3 7 Completed With CC
Block 3 8 Completed With CC
Block 3 9 Completed With CC
Block 3 10 Completed With CC
Block 3 11 Completed With CC
Block 3 12 Completed With CC
Block 4 1 Completed With CC
Block 4 2 Completed With CC
Block 4 3 Completed With CC
Block 4 4 Completed With CC
Block 4 5 Completed With CC
Block 4 6 Completed With CC
Block 4 7 Completed With CC
Block 4 8 Completed With CC
Block 4 9 Completed With CC
Block 4 10 Completed With CC
Block 4 11 Completed With CC
Block 4 12 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facility
2 Electrical Installation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Stairs
2 Completed With CC Club
3 Completed With CC Lift
4 Completed With CC Roof
5 Completed With CC Septic Tank and Sewage Treatment Plant
6 Completed With CC Under Ground Water Reservoir
7 Completed With CC Overhead Tank
8 Completed With CC GYM
9 Completed With CC Indoor Game
10 Completed With CC Library
11 Completed With CC Swimming Pool
12 Completed With CC Yoga Room

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download