VINAYAK AQUASA

Project Status as on Quarter ending 31-03-2025
Updated as on 02-04-2025

Booking Status

  • Residential Apartments Booked
    53

  • Basement Parking Booked
    13

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    40

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK-1 - 1st to 18th Floor - Residential 1 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 2 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 3 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 4 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 5 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 6 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 7 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 8 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 9 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 10 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 11 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 12 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 13 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 14 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 15 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 16 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 17 Completed With CC
BLOCK-1 - 1st to 18th Floor - Residential 18 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilty
2 Drinking Water Facility
3 Main door shutter fixing
4 Aluminum window frame fixing
5 Aluminum slidding door fixing
6 Tiling work for floors
7 Tiling work for walls
8 Putty work
9 Plumbing work ( tower external part )
10 Plumbing work ( internal piping work )
11 Fire line for sprinkler
12 AC work / water line fixing
13 MS Railing
14 Waterproofing Treatment
15 Electrical work ( conduit laying & wiring )
16 Waterproofing Treatment
17 Door frame fixing
18 Door shutter fixing

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Roof
2 Completed With CC External Drainage work
3 Completed With CC Lift
4 Completed With CC Stairs
5 Completed With CC Entry Gate
6 Completed With CC Drive Away
7 Completed With CC Lobby
8 Completed With CC Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download