New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

ORCHARD ESTATE PHASE - II

Project Status as on Quarter ending 31-12-2025
Updated as on 05-01-2026

Booking Status

  • Residential Apartments Booked
    131

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    75

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 6-1st - 4th Floor - residential 1 Under Construction
Block 6-1st - 4th Floor - residential 2 Under Construction
Block 6-1st - 4th Floor - residential 3 Under Construction
Block 6-1st - 4th Floor - residential 4 Under Construction
Block 7-1st - 4th Floor - residential 1 Under Construction
Block 7-1st - 4th Floor - residential 2 Under Construction
Block 7-1st - 4th Floor - residential 3 Under Construction
Block 7-1st - 4th Floor - residential 4 Under Construction
Block 8-1st - 4th Floor - residential 1 Under Construction
Block 8-1st - 4th Floor - residential 2 Under Construction
Block 8-1st - 4th Floor - residential 3 Under Construction
Block 8-1st - 4th Floor - residential 4 Under Construction
Block 9-1st - 4th Floor - residential 1 Under Construction
Block 9-1st - 4th Floor - residential 2 Under Construction
Block 9-1st - 4th Floor - residential 3 Under Construction
Block 9-1st - 4th Floor - residential 4 Under Construction
Block 10-1st - 4th Floor - residential 1 Under Construction
Block 10-1st - 4th Floor - residential 2 Under Construction
Block 10-1st - 4th Floor - residential 3 Under Construction
Block 10-1st - 4th Floor - residential 4 Under Construction
Block 11-1st - 4th Floor - residential 1 Under Construction
Block 11-1st - 4th Floor - residential 2 Under Construction
Block 11-1st - 4th Floor - residential 3 Under Construction
Block 11-1st - 4th Floor - residential 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facilty

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Entrance
2 Under Construction Lobby
3 Not Started Lift
4 Under Construction Stairs
5 Under Construction Terrace
6 Under Construction Parking

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download