New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

IDEAL ROYALE

Project Status as on Quarter ending 31-12-2024
Updated as on 29-01-2025

Booking Status

  • Residential Apartments Booked
    43

  • Basement Parking Booked
    26

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    27

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 23 Completed With CC
1 23 Under Construction
1 23 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 All work Completed
2 Finishing Works in Progress
3 Various Finishing Work in progress
4 various Finishing WIP
5 Finishing WIP
6 Finishing WIP
7 Finishing WIP
8 Finishing WIP
9 Finishing WIP
10 Aluminium Fabrication
11 Brickwork
12 Electrical wip
13 Firefighting work
14 Flooring
15 Plastering work
16 Plumbing
17 HVAC wip
18 Tiling

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Work Completed
2 Under Construction Driveway, Main Gate & Boundry wall
3 Under Construction Drive way & main Gate WIP
4 Under Construction External Brickwork, Plaster & Plumbing WIP
5 Under Construction External B.work, Plaster & ramp WIP.
6 Under Construction External Paint in Progress
7 Under Construction Parking & landscaping WIP
8 Under Construction Electrical & Landscaping WIP
9 Under Construction Waterbody
10 Under Construction Gate no - 2
11 Under Construction Front Side boundary wall

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 04-01-2016 31-03-2016 18-02-2015
Fire NOC 25-02-2015 31-08-2021 12-08-2021
Other 29-04-2014 31-10-2014 13-01-2021