New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

BEGRAJ PRAKRITI PHASE II

Project Status as on Quarter ending 30-09-2025
Updated as on 09-12-2025

Booking Status

  • Residential Apartments Booked
    51

  • Basement Parking Booked
    26

  • Covered Car Parking Booked
    26

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 2 Wing B-1st to 12 th floor- residential 1 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 2 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 3 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 4 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 5 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 6 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 7 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 8 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 9 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 10 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 11 Under Construction
Block 2 Wing B-1st to 12 th floor- residential 12 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facility
2 Fire Facility
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Area
2 Under Construction Entrance
3 Under Construction Lobby
4 Under Construction Stairs
5 Under Construction Lift
6 Under Construction Terrace

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download