WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Eden Richmond Enclave

Project Status as on Quarter ending 31-03-2021
Updated as on 09-04-2021

Booking Status

  • Residential Apartments Booked
    95

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    48

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 Tower 1 4 Under Construction
Block 1 Tower 1 4 Under Construction
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction
Block 2 4 Under Construction
Block 1 Tower 1 4 Under Construction
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction
Block 2 4 Under Construction
Block 1 Tower 1 4 Completed Without CC
Block 1 Tower 2 4 Completed Without CC
Block 1 Tower 3 4 Completed Without CC
Block 1 Tower 4 4 Completed Without CC
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction
Block 2 4 Under Construction
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction
Block 2 4 Under Construction
Block 1 Tower 1 4 Not Started
Block 1 Tower 1 4 Not Started
Block 1 Tower 1 4 Under Construction
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Block 1 T-1 Internal Infrastructure Work not started
2 Block 1 T-2 Internal Infrastructure work not started
3 Block 1 T-3 Internal Infrastructure work not started
4 Block 1 T-4 Internal Infrastructure started
5 Block 2 Internal Infrastructure work started
6 Internal Infrastructure work completed
7 Internal Infrastructure Work Completed Without CC
8 Block 1 T-1 Internal Infrastructure work not started
9 Block 1 T-2 Internal Infrastructure work not started
10 Block 1 T-3 Internal Infrastructure work not started
11 Block 1 T-4 Internal Infrastructure work not started
12 Block 2 Internal Infrastructure work not started
13 Block 1 T-2 Internal Infrastructure Work not started
14 Block 1 T-1 Internal Infrastructure Work not started
15 Block 1 T-3 Internal Infrastructure Work not started
16 Block 1 T-4 Internal Infrastructure Work not started
17 Block 2 Internal Infrastructure Work not started

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction BLOCK 1 TOWER 1 BRICK WORK
2 Under Construction TOWER 3 PLASTER WORK
3 Under Construction Common Area Work
4 Not Started Block 1 T-1 Common Area Work not Started
5 Under Construction Block 1 T-2 Common Area work not started
6 Under Construction Block 1 T-3 Common Area work not started
7 Under Construction Block 1 T-4 Common Area work not started
8 Under Construction Block 2 Common Area work not started
9 Completed Without CC Common Area Work Completed Without CC
10 Not Started Block 1 T-1 common area work not started
11 Under Construction Block 1 T-2 common area work not started
12 Under Construction Block 1 T-3 common area work not started
13 Under Construction Block 1 T-4 common area work not started
14 Under Construction Block 2 common area work not started
15 Under Construction Block 2 common area work not started
16 Not Started Block 1 T-1 Common Area work not started
17 Under Construction Block 1 T-2 Common Area work not started
18 Under Construction Block 1 T-3 Common Area work not started
19 Under Construction Block 1 T-4 Common Area work not started
20 Under Construction Common area work

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download