New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Eden Richmond Enclave

Project Status as on Quarter ending 30-09-2022
Updated as on 29-04-2025

Booking Status

  • Residential Apartments Booked
    124

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    75

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 Tower 1 4 Under Construction
Block 1 Tower 1 4 Under Construction
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction
Block 2 4 Under Construction
Block 1 Tower 1 4 Under Construction
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction
Block 2 4 Under Construction
Block 1 Tower 1 4 Completed Without CC
Block 1 Tower 2 4 Completed Without CC
Block 1 Tower 3 4 Completed Without CC
Block 1 Tower 4 4 Completed Without CC
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction
Block 2 4 Under Construction
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction
Block 2 4 Under Construction
Block 1 Tower 1 4 Not Started
Block 1 Tower 1 4 Not Started
Block 1 Tower 1 4 Under Construction
Block 1 Tower 2 4 Under Construction
Block 1 Tower 3 4 Under Construction
Block 1 Tower 4 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Block 1 T-1 Internal Infrastructure Work not started
2 Block 1 T-2 Internal Infrastructure work not started
3 Block 1 T-3 Internal Infrastructure work not started
4 Block 1 T-4 Internal Infrastructure started
5 Block 2 Internal Infrastructure work started
6 Internal Infrastructure work completed
7 Internal Infrastructure Work Completed Without CC
8 Block 1 T-1 Internal Infrastructure work not started
9 Block 1 T-2 Internal Infrastructure work not started
10 Block 1 T-3 Internal Infrastructure work not started
11 Block 1 T-4 Internal Infrastructure work not started
12 Block 2 Internal Infrastructure work not started
13 Block 1 T-2 Internal Infrastructure Work not started
14 Block 1 T-1 Internal Infrastructure Work not started
15 Block 1 T-3 Internal Infrastructure Work not started
16 Block 1 T-4 Internal Infrastructure Work not started
17 Block 2 Internal Infrastructure Work not started

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction BLOCK 1 TOWER 1 BRICK WORK
2 Under Construction TOWER 3 PLASTER WORK
3 Under Construction Common Area Work
4 Not Started Block 1 T-1 Common Area Work not Started
5 Under Construction Block 1 T-2 Common Area work not started
6 Under Construction Block 1 T-3 Common Area work not started
7 Under Construction Block 1 T-4 Common Area work not started
8 Under Construction Block 2 Common Area work not started
9 Completed Without CC Common Area Work Completed Without CC
10 Not Started Block 1 T-1 common area work not started
11 Under Construction Block 1 T-2 common area work not started
12 Under Construction Block 1 T-3 common area work not started
13 Under Construction Block 1 T-4 common area work not started
14 Under Construction Block 2 common area work not started
15 Under Construction Block 2 common area work not started
16 Not Started Block 1 T-1 Common Area work not started
17 Under Construction Block 1 T-2 Common Area work not started
18 Under Construction Block 1 T-3 Common Area work not started
19 Under Construction Block 1 T-4 Common Area work not started
20 Under Construction Common area work

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download