WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Please be informed that the last date for Quarterly Update of Registered Projects has been extended as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

FORTUNE SKY

Project Status as on Quarter ending 31-12-2024
Updated as on 20-01-2025

Booking Status

  • Residential Apartments Booked
    1

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Not Started
1 3 Not Started
1 4 Not Started
1 5 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facility
2 Emergency Evacuation Service

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Stairs
2 Under Construction Lift
3 Not Started Lobby
4 Not Started Roof
5 Not Started Septic Tank
6 Not Started Underground Water Reservoir
7 Not Started Overhead Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download