New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Tarang Tower 6&7

Project Status as on Quarter ending 30-06-2025
Updated as on 07-07-2025

Booking Status

  • Residential Apartments Booked
    72

  • Basement Parking Booked
    45

  • Covered Car Parking Booked
    20

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 6- residential 1 Completed With CC
Tower 6- residential 2 Completed With CC
Tower 6- residential 3 Completed With CC
Tower 6- residential 4 Completed With CC
Tower 6- residential 5 Completed With CC
Tower 6- residential 6 Completed With CC
Tower 6- residential 7 Completed With CC
Tower 6- residential 8 Completed With CC
Tower 6- residential 9 Completed With CC
Tower 6- residential 10 Completed With CC
Tower 6- residential 11 Completed With CC
Tower 6- residential 12 Completed With CC
Tower 7- Residential 1 Completed Without CC
Tower 7- Residential 2 Completed Without CC
Tower 7- Residential 3 Completed Without CC
Tower 7- Residential 4 Completed Without CC
Tower 7- Residential 5 Completed Without CC
Tower 7- Residential 6 Completed Without CC
Tower 7- Residential 7 Completed Without CC
Tower 7- Residential 8 Completed Without CC
Tower 7- Residential 9 Completed Without CC
Tower 7- Residential 10 Completed Without CC
Tower 7- Residential 11 Completed Without CC
Tower 7- Residential 12 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Fire Fighting Facilty
3 Emergency Evacuation Services
4 Use of Renewable Energy

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Stair case
2 Completed Without CC Lift
3 Completed Without CC Roof
4 Completed Without CC Main gate
5 Completed Without CC Lobby

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download