WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Tarang Tower 6&7

Project Status as on Quarter ending 31-12-2024
Updated as on 27-02-2025

Booking Status

  • Residential Apartments Booked
    144

  • Basement Parking Booked
    88

  • Covered Car Parking Booked
    46

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 6- residential 1 Completed With CC
Tower 6- residential 2 Completed With CC
Tower 6- residential 3 Completed With CC
Tower 6- residential 4 Completed With CC
Tower 6- residential 5 Completed With CC
Tower 6- residential 6 Completed With CC
Tower 6- residential 7 Completed With CC
Tower 6- residential 8 Completed With CC
Tower 6- residential 9 Completed With CC
Tower 6- residential 10 Completed With CC
Tower 6- residential 11 Completed With CC
Tower 6- residential 12 Completed With CC
Tower 7- Residential 1 Under Construction
Tower 7- Residential 2 Under Construction
Tower 7- Residential 3 Under Construction
Tower 7- Residential 4 Under Construction
Tower 7- Residential 5 Under Construction
Tower 7- Residential 6 Under Construction
Tower 7- Residential 7 Under Construction
Tower 7- Residential 8 Under Construction
Tower 7- Residential 9 Under Construction
Tower 7- Residential 10 Under Construction
Tower 7- Residential 11 Under Construction
Tower 7- Residential 12 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Entrance
2 Completed With CC Lobby

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download