New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

MARUTI HEIGHTS

Project Status as on Quarter ending 30-09-2025
Updated as on 25-09-2025

Booking Status

  • Residential Apartments Booked
    25

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 4 Under Construction
1 4 Under Construction
1 1 Under Construction
1 4 Under Construction
1 4 Under Construction
1 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 not started
2 not started
3 85% of internal infrastructure completed
4 TILES FLOORING UNDER PROCESS
5 BRICK WALL / PLASTER UNDER PROCESS
6 90% of construction of internal infrastructure
7 90% of internal infrastructure completed
8 Internal walls, Internal Plaster under process

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction First Floor Stair started
2 Under Construction First Floor Stair started
3 Under Construction 80% of construction of common area completed
4 Under Construction LIFT WELL, OVERHEAD AND UNDERGROUND WATER TANK UNDER PROCESS
5 Under Construction 90% of comon area completed
6 Under Construction 85% of consructions of common area completed
7 Under Construction Staircase and Lobbies at each floor level connecting staircase completed

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download