Project Status as on Quarter ending 31-03-2025
Updated as on 05-04-2025

Booking Status

  • Residential Apartments Booked
    131

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    111

  • Mechanical Parking Booked
    19

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 2 7 Under Construction
Tower 2 8 Under Construction
Tower 2 7 Under Construction
Tower 2 8 Under Construction
Tower 1 1 Under Construction
Tower 1 2 Under Construction
Tower 1 3 Under Construction
Tower 1 4 Under Construction
Tower 1 5 Under Construction
Tower 1 6 Under Construction
Tower 1 7 Under Construction
Tower 1 8 Under Construction
Tower 2 1 Under Construction
Tower 2 2 Under Construction
Tower 2 3 Under Construction
Tower 2 4 Under Construction
Tower 2 5 Under Construction
Tower 2 6 Under Construction
Tower 3 1 Under Construction
Tower 3 2 Under Construction
Tower 3 3 Under Construction
Tower 3 4 Under Construction
Tower 3 5 Under Construction
Tower 3 6 Under Construction
Tower 3 7 Under Construction
Tower 3 8 Under Construction
Tower 4 1 Under Construction
Tower 4 2 Under Construction
Tower 4 3 Under Construction
Tower 4 4 Under Construction
Tower 4 5 Under Construction
Tower 4 7 Under Construction
Tower 4 6 Under Construction
Tower 4 8 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Common Areas
2 Elevation Tower 1
3 Elevation Tower 2
4 Elevation Tower 3
5 Elevation Tower 4

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Areas

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Such other approvals as may be required and obtained for the project 20-01-2025 20-01-2025 20-01-2025 RERA Order Compliance Architect Certificate