WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Siddha Galaxia - Phase II

Project Status as on Quarter ending 31-12-2023
Updated as on 08-11-2024

Booking Status

  • Residential Apartments Booked
    638

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    508

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK - 7A (OPHELIA) 1 Completed With CC
BLOCK - 7A (OPHELIA) 2 Completed With CC
BLOCK - 7A (OPHELIA) 3 Completed With CC
BLOCK - 7A (OPHELIA) 4 Completed With CC
BLOCK - 7A (OPHELIA) 5 Completed With CC
BLOCK - 7A (OPHELIA) 6 Completed With CC
BLOCK - 7A (OPHELIA) 7 Completed With CC
BLOCK - 7A (OPHELIA) 8 Completed With CC
BLOCK - 7A (OPHELIA) 9 Completed With CC
BLOCK - 7A (OPHELIA) 10 Completed With CC
BLOCK - 7A (OPHELIA) 11 Completed With CC
BLOCK - 7A (OPHELIA) 12 Completed With CC
BLOCK - 7A (OPHELIA) 13 Completed With CC
BLOCK - 7B (BIANCA) 1 Completed With CC
BLOCK - 7B (BIANCA) 2 Completed With CC
BLOCK - 7B (BIANCA) 3 Completed With CC
BLOCK - 7B (BIANCA) 4 Completed With CC
BLOCK - 7B (BIANCA) 5 Completed With CC
BLOCK - 7B (BIANCA) 6 Completed With CC
BLOCK - 7B (BIANCA) 7 Completed With CC
BLOCK - 7B (BIANCA) 8 Completed With CC
BLOCK - 7B (BIANCA) 9 Completed With CC
BLOCK - 7B (BIANCA) 10 Completed With CC
BLOCK - 7B (BIANCA) 11 Completed With CC
BLOCK - 7B (BIANCA) 12 Completed With CC
BLOCK - 7B (BIANCA) 13 Completed With CC
BLOCK - 7C (ORION) 1 Completed With CC
BLOCK - 7C (ORION) 2 Completed With CC
BLOCK - 7C (ORION) 3 Completed With CC
BLOCK - 7C (ORION) 4 Completed With CC
BLOCK - 7C (ORION) 5 Completed With CC
BLOCK - 7C (ORION) 6 Completed With CC
BLOCK - 7C (ORION) 7 Completed With CC
BLOCK - 7C (ORION) 8 Completed With CC
BLOCK - 7C (ORION) 9 Completed With CC
BLOCK - 7C (ORION) 10 Completed With CC
BLOCK - 7C (ORION) 11 Completed With CC
BLOCK - 7C (ORION) 12 Completed With CC
BLOCK - 7C (ORION) 13 Completed With CC
BLOCK - 7D (CYGNUS) 1 Completed With CC
BLOCK - 7D (CYGNUS) 2 Completed With CC
BLOCK - 7D (CYGNUS) 3 Completed With CC
BLOCK - 7D (CYGNUS) 4 Completed With CC
BLOCK - 7D (CYGNUS) 5 Completed With CC
BLOCK - 7D (CYGNUS) 6 Completed With CC
BLOCK - 7D (CYGNUS) 7 Completed With CC
BLOCK - 7D (CYGNUS) 8 Completed With CC
BLOCK - 7D (CYGNUS) 9 Completed With CC
BLOCK - 7D (CYGNUS) 10 Completed With CC
BLOCK - 7D (CYGNUS) 11 Completed With CC
BLOCK - 7D (CYGNUS) 12 Completed With CC
BLOCK - 7D (CYGNUS) 13 Completed With CC
BLOCK - 7E (PHOENIX) 1 Completed With CC
BLOCK - 7E (PHOENIX) 2 Completed With CC
BLOCK - 7E (PHOENIX) 3 Completed With CC
BLOCK - 7E (PHOENIX) 4 Completed With CC
BLOCK - 7E (PHOENIX) 5 Completed With CC
BLOCK - 7E (PHOENIX) 6 Completed With CC
BLOCK - 7E (PHOENIX) 7 Completed With CC
BLOCK - 7E (PHOENIX) 8 Completed With CC
BLOCK - 7E (PHOENIX) 9 Completed With CC
BLOCK - 7E (PHOENIX) 10 Completed With CC
BLOCK - 7E (PHOENIX) 11 Completed With CC
BLOCK - 7E (PHOENIX) 12 Completed With CC
BLOCK - 7E (PHOENIX) 13 Completed With CC
BLOCK - 10 (ATLAS) 1 Completed With CC
BLOCK - 10 (ATLAS) 2 Completed With CC
BLOCK - 10 (ATLAS) 3 Completed With CC
BLOCK - 10 (ATLAS) 4 Completed With CC
BLOCK - 10 (ATLAS) 5 Completed With CC
BLOCK - 10 (ATLAS) 6 Completed With CC
BLOCK - 10 (ATLAS) 7 Completed With CC
BLOCK - 10 (ATLAS) 8 Completed With CC
BLOCK - 10 (ATLAS) 9 Completed With CC
BLOCK - 10 (ATLAS) 10 Completed With CC
BLOCK - 10 (ATLAS) 11 Completed With CC
BLOCK - 10 (ATLAS) 12 Completed With CC
BLOCK - 10 (ATLAS) 13 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities
2 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Stairs
2 Completed With CC Lift
3 Completed With CC Lobby
4 Completed With CC Roof
5 Completed With CC Septic Tank
6 Completed With CC Under-Ground Water Reservoir
7 Completed With CC Overhead Tank
8 Completed Without CC Mechanical Car Parking
9 Completed With CC Sewage Treatment Plant
10 Completed With CC Water Filtration Plant
11 Completed Without CC Club

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download