WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    The last date for all the pending quarterly project updates has been extended till 30.04.2025,please upload all the pending quarterly updates within 30.04.2025 to avoid penalty.

"Solitary Heights"

Project Status as on Quarter ending 31-03-2025
Updated as on 07-04-2025

Booking Status

  • Residential Apartments Booked
    1

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Residential 1 Under Construction
Residential 2 Under Construction
Residential 3 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download