New Please be informed that the last date for Quarterly Update of Registered Projects has been extended as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

Botanica Phase II

Project Status as on Quarter ending 30-09-2024
Updated as on 07-10-2024

Booking Status

  • Residential Apartments Booked
    12

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    12

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
100 1 Under Construction
101 1 Under Construction
102 1 Under Construction
103 1 Under Construction
104 1 Under Construction
105 1 Under Construction
106 1 Under Construction
107 1 Under Construction
108 1 Under Construction
109 1 Under Construction
110 1 Under Construction
111 1 Under Construction
112 1 Under Construction
113 1 Under Construction
114 1 Under Construction
115 1 Under Construction
116 1 Under Construction
117 1 Under Construction
118 1 Under Construction
119 1 Under Construction
120 1 Under Construction
121 1 Under Construction
122 1 Under Construction
123 1 Under Construction
124 1 Under Construction
125 1 Under Construction
126 1 Under Construction
127 1 Under Construction
128 1 Under Construction
129 1 Under Construction
130 1 Under Construction
131 1 Under Construction
132 1 Under Construction
133 1 Under Construction
134 1 Under Construction
135 1 Under Construction
136 1 Under Construction
137 1 Under Construction
138 1 Under Construction
139 1 Under Construction
140 1 Under Construction
141 1 Under Construction
142 1 Under Construction
143 1 Under Construction
144 1 Under Construction
145 1 Under Construction
146 1 Under Construction
147 1 Under Construction
148 1 Under Construction
149 1 Under Construction
150 1 Under Construction
151 1 Under Construction
152 1 Under Construction
153 1 Under Construction
154 1 Under Construction
155 1 Under Construction
156 1 Under Construction
157 1 Under Construction
158 1 Under Construction
159 1 Under Construction
160 1 Under Construction
161 1 Under Construction
162 1 Under Construction
163 1 Under Construction
164 1 Under Construction
165 1 Under Construction
166 1 Under Construction
167 1 Under Construction
168 1 Under Construction
169 1 Under Construction
170 1 Under Construction
171 1 Under Construction
172 1 Under Construction
173 1 Under Construction
174 1 Under Construction
175 1 Under Construction
176 1 Under Construction
177 1 Under Construction
178 1 Under Construction
179 1 Under Construction
180 1 Under Construction
181 1 Under Construction
182 1 Under Construction
183 1 Under Construction
184 1 Under Construction
185 1 Under Construction
186 1 Under Construction
187 1 Under Construction
188 1 Under Construction
189 1 Under Construction
190 1 Under Construction
191 1 Under Construction
192 1 Under Construction
193 1 Under Construction
194 1 Under Construction
195 1 Under Construction
196 1 Under Construction
197 1 Under Construction
198 1 Under Construction
199 1 Under Construction
200 1 Under Construction
201 1 Under Construction
202 1 Under Construction
203 1 Under Construction
204 1 Under Construction
205 1 Under Construction
206 1 Under Construction
207 1 Under Construction
208 1 Under Construction
209 1 Under Construction
210 1 Under Construction
211 1 Under Construction
212 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Use of Renewable Energy
2 Pile work phase -II
3 Water Facility
4 Fire Facility
5 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Road
2 Under Construction Lobby
3 Under Construction Lift
4 Under Construction Stair Case
5 Under Construction Roof
6 Under Construction Septic Tank
7 Under Construction Power Backup

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download