New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

ARVINTH HOMES

Project Status as on Quarter ending 31-12-2025
Updated as on 07-01-2026

Booking Status

  • Residential Apartments Booked
    4

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed Without CC
1 2 Under Construction
2 1 Completed Without CC
2 2 Under Construction
1 1 Not Started
1 2 Not Started
1 3 Not Started
1 4 Not Started
2 1 Not Started
2 2 Not Started
2 3 Not Started
2 4 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Extinguisher Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Piiling Work
2 Under Construction STAIRS
3 Under Construction LOBBY
4 Not Started Stairs
5 Not Started Lift
6 Not Started Lobby
7 Not Started Roof
8 Not Started Septic Tank
9 Not Started Under Ground Water Reservoir
10 Not Started Overhead Tank
11 Not Started Community Hall
12 Not Started Kids Playground

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download