AURA (Phase-II)

Project Status as on Quarter ending 31-03-2021
Updated as on 05-04-2021

Booking Status

  • Residential Apartments Booked
    51

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    17

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
4 1 Completed With CC
4 2 Completed With CC
4 3 Completed With CC
4 4 Completed With CC
4 5 Completed With CC
4 6 Completed With CC
4 7 Completed With CC
4 8 Completed With CC
4 9 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Road,STP and RHT

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Aura-Common Area
2 Completed With CC Aura-Club

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Such other approvals as may be required and obtained for the project 16-10-2019 30-10-2019 23-10-2019