WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

ECOSPACE BUSINESS TOWERS

Project Status as on Quarter ending 30-09-2024
Updated as on 07-10-2024

Booking Status

  • Commercial Unit Booked
    450

  • Basement Parking Booked
    86

  • Covered Car Parking Booked
    374

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
TOWER-5A 1 Under Construction
TOWER-5A 2 Under Construction
TOWER-5A 3 Under Construction
TOWER-5A 4 Under Construction
TOWER-5A 5 Under Construction
TOWER-5A 6 Under Construction
TOWER-5A 7 Under Construction
TOWER-5A 8 Under Construction
TOWER-5A 9 Under Construction
TOWER-5A 10 Under Construction
TOWER-5A 11 Under Construction
TOWER-5B 1 Under Construction
TOWER-5B 2 Under Construction
TOWER-5B 3 Under Construction
TOWER-5B 4 Under Construction
TOWER-5B 5 Under Construction
TOWER-5B 6 Under Construction
TOWER-5B 7 Under Construction
TOWER-5B 8 Under Construction
TOWER-5B 9 Under Construction
TOWER-5B 10 Not Started
TOWER-5B 11 Under Construction
TOWER-5C 1 Under Construction
TOWER-5C 2 Under Construction
TOWER-5C 3 Under Construction
TOWER-5C 4 Under Construction
TOWER-5C 5 Under Construction
TOWER-5C 6 Under Construction
TOWER-5C 7 Under Construction
TOWER-5C 8 Under Construction
TOWER-5C 9 Under Construction
TOWER-5C 10 Under Construction
TOWER-5C 11 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 • Fire Protection and Detection System
2 • Public address & voice evacuation system
3 • Passenger & service elevators
4 • DG Power Back up
5 • Internal sewer & storm water line
6 • Security surveillance system

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Landscaping

Approval for NOC