New Please be informed that the The last date for submission of Quarterly Update of Registered Real Estate Projects is hereby extended tillĀ 28.02.2025 as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

TORSA ABASAN

Project Status as on Quarter ending 31-12-2024
Updated as on 29-01-2025

Booking Status

  • Residential Apartments Booked
    4

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    1

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
A 1 Under Construction
A 2 Under Construction
A 3 Under Construction
A 4 Under Construction
A 5 Not Started
B 1 Under Construction
B 2 Under Construction
B 3 Under Construction
B 4 Under Construction
B 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1
2

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Stairs
2 Under Construction Lift
3 Under Construction Roof
4 Completed Without CC Septic Tank
5 Under Construction Parking
6 Under Construction Water Reservoir

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Fire NOC 16-05-2023 09-06-2023 16-06-2023
Consent to Establish and Operate 07-12-2022 31-03-2025 29-12-2025
Such other approvals as may be required and obtained for the project 13-06-2022 13-07-2022 23-07-2022