Merlin Oikyo Phase 1

Project Status as on Quarter ending 31-03-2025
Updated as on 07-04-2025

Booking Status

  • Residential Apartments Booked
    225

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    41

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
2 1 Under Construction
3 2 Under Construction
7 1 Under Construction
8 3 Under Construction
9 3 Under Construction
5 2 Under Construction
6 3 Under Construction
2 2 Under Construction
2 4 Under Construction
3 3 Under Construction
3 4 Under Construction
5 4 Under Construction
7 3 Under Construction
7 4 Under Construction
6 1 Under Construction
6 4 Under Construction
8 2 Under Construction
8 4 Under Construction
9 1 Under Construction
9 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drive Way

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Area

Approval for NOC