New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

EDEN TOLLY SIGNATURE PLUS

Project Status as on Quarter ending 30-09-2019
Updated as on 29-04-2025

Booking Status

  • Residential Apartments Booked
    68

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    34

  • Mechanical Parking Booked
    23

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
344/1 MG Road, Kolkata - 700104 12 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure Completed
2 Internal infrastructure work completed
3 Internal infrastructure work completed
4 Flat inside work completed

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Common Area work Completed
2 Completed Without CC Common Driveway work completed
3 Completed Without CC Common Lobby Work completed
4 Completed Without CC Common staircase work completed

Approval for NOC