SERENE TEMPLE CITY PHASE- III

Project Status as on Quarter ending 31-03-2025
Updated as on 09-04-2025

Booking Status

  • Residential Apartments Booked
    6

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    1

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK 1 1 Under Construction
BLOCK 1 2 Under Construction
BLOCK 1 3 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 STAIR AREA OF GROUND FLOOR, 1ST FLOOR, 2ND FLOOR

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction ROOF
2 Under Construction COMMON TOILET

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 07-11-2024 31-01-2025 31-01-2025