WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     Applications are invited from the eligible and willing persons for the position of (i) Judicial Member of West Bengal Real Estate Appellate Tribunal (WBREAT) and (ii) Member of West Bengal Real Estate Regulatory Authority (WBRERA) Click here to open;    

Rameswara Riverview Phase II

Project Status as on Quarter ending 31-12-2025
Updated as on 27-01-2026

Booking Status

  • Residential Apartments Booked
    28

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    19

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 5 - Ground - Commercial 1 Under Construction
Block 5 1st to 4th - Residential 1 Under Construction
Block 5 1st to 4th - Residential 2 Under Construction
Block 5 1st to 4th - Residential 3 Under Construction
Block 5 1st to 4th - Residential 4 Under Construction
Block - 6 - Ground- Commercial 1 Not Started
Block 6 - 1st to 4th Floor - Residential 1 Not Started
Block 6 - 1st to 4th Floor - Residential 2 Not Started
Block 6 - 1st to 4th Floor - Residential 3 Not Started
Block 6 - 1st to 4th Floor - Residential 4 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Emergency Evacaution
2 Water Facilities
3 Fire Facilites

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Terrace
2 Not Started Entrance
3 Not Started Lobby
4 Not Started Staircase
5 Not Started Lift

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download