WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Magnolia Fantasia Phase - I

Project Status as on Quarter ending 31-03-2021
Updated as on 29-04-2021

Booking Status

  • Residential Apartments Booked
    171

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    37

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
2 1 Under Construction
2 2 Under Construction
2 3 Under Construction
2 4 Under Construction
3 1 Under Construction
3 2 Under Construction
3 3 Under Construction
3 4 Under Construction
4 1 Under Construction
4 2 Under Construction
4 3 Under Construction
4 4 Under Construction
5 1 Under Construction
5 2 Under Construction
5 3 Under Construction
5 4 Under Construction
6 1 Under Construction
6 2 Under Construction
6 3 Under Construction
6 4 Under Construction
7 1 Under Construction
7 2 Under Construction
7 3 Under Construction
7 4 Under Construction
8 1 Under Construction
8 2 Under Construction
8 3 Under Construction
8 4 Under Construction
9 1 Under Construction
9 2 Under Construction
9 3 Under Construction
9 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities
2 Electrical Installation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Lift
2 Not Started Lobby
3 Not Started Roof
4 Not Started Septic Tank
5 Not Started Under Ground Water Reservoir
6 Not Started Overhead Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download