New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

UNIMARK SPORTS CITY - PHASE 1

Project Status as on Quarter ending 31-03-2025
Updated as on 09-04-2025

Booking Status

  • Residential Apartments Booked
    0

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 5 Not Started
1 6 Not Started
1 7 Not Started
2 1 Not Started
1 1 Not Started
1 2 Not Started
1 3 Not Started
1 4 Not Started
2 2 Not Started
2 3 Not Started
2 4 Not Started
2 5 Not Started
2 6 Not Started
2 7 Not Started
3 1 Not Started
3 2 Not Started
3 3 Not Started
3 4 Not Started
3 7 Not Started
4 1 Not Started
4 2 Not Started
4 3 Not Started
4 4 Not Started
4 5 Not Started
4 6 Not Started
4 7 Not Started
5 1 Not Started
5 2 Not Started
5 3 Not Started
5 4 Not Started
5 5 Not Started
5 6 Not Started
5 7 Not Started
6 1 Not Started
6 2 Not Started
6 3 Not Started
6 4 Not Started
6 5 Not Started
6 6 Not Started
6 7 Not Started
7 1 Not Started
7 2 Not Started
7 3 Not Started
7 4 Not Started
7 5 Not Started
7 6 Not Started
7 7 Not Started
8 1 Not Started
8 2 Not Started
8 3 Not Started
8 4 Not Started
8 5 Not Started
8 6 Not Started
8 7 Not Started
9 1 Not Started
9 2 Not Started
9 3 Not Started
9 4 Not Started
9 5 Not Started
9 6 Not Started
9 7 Not Started
10 1 Not Started
10 2 Not Started
10 3 Not Started
10 4 Not Started
10 5 Not Started
10 6 Not Started
10 7 Not Started
Commercial 1 Not Started
Commercial 2 Not Started
3 5 Not Started
3 6 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Emergency Evacuation
2 Fire Fighting Facilities
3 Electrical Installation
4 Solar Energy
5 Water Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Power Backup
2 Not Started Stairs
3 Not Started Lift
4 Not Started Lobby
5 Not Started Septic Tank
6 Not Started Overhead tank
7 Not Started Roof
8 Not Started Underground Water Reservoir

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download