WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    The last date for all the pending quarterly project updates has been extended till 30.04.2025,please upload all the pending quarterly updates within 30.04.2025 to avoid penalty.

SERENE TEMPLE CITY PHASE- IV

Project Status as on Quarter ending 31-03-2025
Updated as on 09-04-2025

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK 1 1 Under Construction
BLOCK 1 2 Under Construction
BLOCK 1 3 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 CARE TAKER ROOM

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction ROOF TOP AREA

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download