New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

SUNRISE AURA PHASE II

Project Status as on Quarter ending 31-12-2025
Updated as on 06-01-2026

Booking Status

  • Residential Apartments Booked
    29

  • Basement Parking Booked
    17

  • Covered Car Parking Booked
    10

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
6 1 Under Construction
6 2 Not Started
6 3 Not Started
6 4 Not Started
6 5 Not Started
6 6 Not Started
6 7 Not Started
6 8 Not Started
6 9 Not Started
6 10 Not Started
6 11 Not Started
6 12 Not Started
6 13 Not Started
6 14 Not Started
6 15 Not Started
6 16 Not Started
6 17 Not Started
6 18 Not Started
7 1 Under Construction
7 2 Under Construction
7 3 Under Construction
7 4 Under Construction
7 5 Under Construction
7 6 Under Construction
7 7 Under Construction
7 8 Under Construction
7 9 Under Construction
7 10 Under Construction
7 11 Under Construction
7 12 Under Construction
7 13 Not Started
7 14 Not Started
7 15 Not Started
7 16 Not Started
7 17 Not Started
7 18 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilties
2 Electrical Installation
3 Emergency Evacuation
4 Water Facility
5 RENEWABLE ENERGY

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Club
2 Under Construction Stairs
3 Under Construction Lift
4 Not Started Lobby
5 Under Construction Septic Tank
6 Not Started Over Head Tank
7 Under Construction Underground Water Reservoir
8 Not Started Power Backup
9 Not Started Roof
10 Under Construction PLAYGROUND ON PODIUM TOP
11 Under Construction Swimming Pool
12 Under Construction Kids Pool
13 Under Construction Jogging Track
14 Under Construction Outdoor Children's Play Zone
15 Under Construction Badminton Court
16 Not Started Serenity Trellis
17 Under Construction ELEVATED WALKING TRAIL
18 Under Construction MINI AMPHITHEATRE
19 Under Construction SUNRISE LOUNGE
20 Under Construction ROLLER SKATING AREA
21 Under Construction POOL DECK
22 Under Construction SHADED SEATING AREA
23 Not Started EMERALD LAWN
24 Under Construction MEDITATION ZONE
25 Under Construction MEDITATION ZONE
26 Under Construction MINI CRICKET PRACTICE AREA
27 Under Construction TROPICAL FLOWER GARDEN
28 Under Construction FESTIVE ZONE
29 Not Started CENTRAL POINT

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download