New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     Applications are invited from the eligible and willing persons for the position of (i) Judicial Member of West Bengal Real Estate Appellate Tribunal (WBREAT) and (ii) Member of West Bengal Real Estate Regulatory Authority (WBRERA) Click here to open;    

SERENIA PHASE - I

Project Status as on Quarter ending 31-03-2026
Updated as on 06-04-2026

Booking Status

  • Residential Apartments Booked
    454

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    200

  • Mechanical Parking Booked
    238

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 4 28 Not Started
Tower 1 1 Under Construction
Tower 1 2 Under Construction
Tower 1 3 Under Construction
Tower 1 4 Under Construction
Tower 1 5 Under Construction
Tower 1 6 Under Construction
Tower 1 7 Under Construction
Tower 1 8 Under Construction
Tower 1 9 Under Construction
Tower 1 10 Under Construction
Tower 1 11 Under Construction
Tower 1 12 Under Construction
Tower 1 13 Under Construction
Tower 1 14 Under Construction
Tower 1 15 Under Construction
Tower 1 16 Under Construction
Tower 1 17 Under Construction
Tower 1 20 Not Started
Tower 1 21 Not Started
Tower 1 22 Not Started
Tower 1 23 Not Started
Tower 1 24 Not Started
Tower 1 25 Not Started
Tower 1 26 Not Started
Tower 1 27 Not Started
Tower 1 28 Not Started
Tower 2 1 Under Construction
Tower 2 2 Not Started
Tower 2 3 Not Started
Tower 2 4 Not Started
Tower 2 5 Not Started
Tower 2 6 Not Started
Tower 2 7 Not Started
Tower 2 8 Not Started
Tower 2 9 Not Started
Tower 2 10 Not Started
Tower 2 11 Not Started
Tower 2 12 Not Started
Tower 2 13 Not Started
Tower 2 14 Not Started
Tower 2 15 Not Started
Tower 2 16 Not Started
Tower 2 17 Not Started
Tower 2 18 Not Started
Tower 2 19 Not Started
Tower 2 20 Not Started
Tower 2 21 Not Started
Tower 2 22 Not Started
Tower 2 23 Not Started
Tower 2 24 Not Started
Tower 2 25 Not Started
Tower 2 26 Not Started
Tower 2 27 Not Started
Tower 2 28 Not Started
Tower 3 Ground 1 Under Construction
Tower 3 1 Under Construction
Tower 3 2 Not Started
Tower 3 3 Not Started
Tower 3 4 Not Started
Tower 3 5 Not Started
Tower 3 6 Not Started
Tower 3 7 Not Started
Tower 3 8 Not Started
Tower 3 9 Not Started
Tower 3 10 Not Started
Tower 3 11 Not Started
Tower 3 12 Not Started
Tower 3 13 Not Started
Tower 3 14 Not Started
Tower 3 15 Not Started
Tower 3 16 Not Started
Tower 3 17 Not Started
Tower 3 18 Not Started
Tower 3 19 Not Started
Tower 3 20 Not Started
Tower 3 21 Not Started
Tower 3 22 Not Started
Tower 3 23 Not Started
Tower 3 24 Not Started
Tower 3 25 Not Started
Tower 3 26 Not Started
Tower 3 27 Not Started
Tower 3 28 Not Started
Tower 4 Ground 1 Under Construction
Tower 4 1 Under Construction
Tower 4 2 Not Started
Tower 4 3 Not Started
Tower 4 4 Not Started
Tower 4 5 Not Started
Tower 4 6 Not Started
Tower 4 7 Not Started
Tower 4 8 Not Started
Tower 4 9 Not Started
Tower 4 10 Not Started
Tower 4 11 Not Started
Tower 4 12 Not Started
Tower 4 13 Not Started
Tower 4 14 Not Started
Tower 4 15 Not Started
Tower 4 16 Not Started
Tower 4 17 Not Started
Tower 4 18 Not Started
Tower 4 19 Not Started
Tower 4 20 Not Started
Tower 4 21 Not Started
Tower 4 22 Not Started
Tower 4 23 Not Started
Tower 4 24 Not Started
Tower 4 25 Not Started
Tower 4 26 Not Started
Tower 4 27 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Use of Renewable Energy
2 Drinking Water Facility
3 Emergency Evacuation Services
4 Fire Fighting Facilty

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Main Gate
2 Under Construction Lobby
3 Under Construction Staircase
4 Not Started Lift
5 Not Started Terrace

Approval for NOC