Project Status as on Quarter ending 31-03-2021 Updated as on 09-04-2021
Booking Status
Residential Apartments Booked
74
Basement Parking Booked Not mentioned
Covered Car Parking Booked 44
Mechanical Parking Booked Not mentioned
Status of construction of each building/floor with photographs
Block/Building
Floor
Construction Status
Download
BLOCK -1
1
Not Started
BLOCK -1
2
Not Started
BLOCK -1
3
Not Started
BLOCK -1
4
Not Started
BLOCK -2 (PART -1)
1
Not Started
BLOCK -2 (PART -1)
2
Not Started
BLOCK -2 (PART -1)
3
Not Started
BLOCK -2 (PART -1)
4
Not Started
BLOCK - 2 (PART - 2)
1
Under Construction
BLOCK - 2 (PART - 2)
2
Not Started
BLOCK - 2 (PART - 2)
3
Not Started
BLOCK - 2 (PART - 2)
4
Not Started
BLOCK - 2 (PART - 3)
1
Under Construction
BLOCK - 2 (PART - 3)
2
Under Construction
BLOCK - 2 (PART - 3)
3
Under Construction
BLOCK - 2 (PART - 3)
4
Under Construction
BLOCK -1
1
Under Construction
BLOCK -1
2
Not Started
BLOCK -1
3
Not Started
BLOCK -1
4
Not Started
BLOCK -2 (PART -1)
1
Not Started
BLOCK -2 (PART -1)
2
Not Started
BLOCK -2 (PART -1)
3
Not Started
BLOCK -2 (PART -1)
4
Not Started
BLOCK - 2 (PART - 2)
1
Under Construction
BLOCK - 2 (PART - 2)
2
Under Construction
BLOCK - 2 (PART - 2)
3
Under Construction
BLOCK - 2 (PART - 2)
4
Under Construction
BLOCK - 2 (PART - 3)
1
Under Construction
BLOCK - 2 (PART - 3)
2
Under Construction
BLOCK - 2 (PART - 3)
3
Under Construction
BLOCK - 2 (PART - 3)
4
Under Construction
BLOCK -1
1
Under Construction
BLOCK -1
2
Under Construction
BLOCK -1
3
Under Construction
BLOCK -1
4
Under Construction
BLOCK -2 (PART -1)
1
Under Construction
BLOCK -2 (PART -1)
2
Under Construction
BLOCK -2 (PART -1)
3
Under Construction
BLOCK -2 (PART -1)
4
Under Construction
BLOCK - 2 (PART - 2)
1
Under Construction
BLOCK - 2 (PART - 2)
2
Under Construction
BLOCK - 2 (PART - 2)
3
Under Construction
BLOCK - 2 (PART - 2)
4
Under Construction
BLOCK - 2 (PART - 3)
1
Under Construction
BLOCK - 2 (PART - 3)
2
Under Construction
BLOCK - 2 (PART - 3)
3
Under Construction
BLOCK - 2 (PART - 3)
4
Under Construction
Status of Construction of Internal Infrastructure with photographs
Sl No.
Title
Download
1
2
AAC Brick work , 1 to 4th floor completed in block 2 part 3 , 1st floor slab structure completed in block 1, foundation structure completed in block 2 part 1, up to roof structure completed in block 2 part 2
3
BLOCK 1 - 2ND FLOOR SLAB STRUCTURE COMPLETED
4
BLOCK 2 PART 1 - 1ST FLOOR SLAB STRUCTURE COMPLETED
5
BLOCK 2 PART 2 - UPTO ABOVE ROOF STRUCTURE COMPLETED , AAC BLOCK WORK 1ST TO 4TH FLOOR GOING ON
6
BLOCK 2 PART 3 - UPTO ABOVE ROOF STRUCTURE COMPLETED , 1ST TO 4TH AAC BLOCK WORK AND INTERNAL PLASTER GOING ON
Status of Construction of Common Areas with photographs
Sl No.
Construction Status
Description
Download
1
Under Construction
BLOCK -2 (PART -1)- FOUNDATION WORK
2
Under Construction
BLOCK -2 (PART-2) UPTO 1ST FLOOR CASTING
3
Under Construction
BLOCK - 2 (PART-3 ) UPTO ABOVE ROOF
4
Not Started
not started yet
5
Not Started
COMMON AREA WORK NOT STARTED YET FOR THE BLOCK 1, BLOCK 2 PART 1, 2 & 3.