New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

Avenida

Project Status as on Quarter ending 31-03-2021
Updated as on 14-04-2021

Booking Status

  • Residential Apartments Booked
    781

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    851

  • Covered Car Parking Booked
    40

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower-G_residential 1 Under Construction
Tower-F 5 Completed With CC
Tower-F 18 Completed With CC
Tower-E 1 Completed With CC
Tower-E 2 Completed With CC
Tower-E 3 Completed With CC
Tower-E 4 Completed With CC
Tower-E 5 Completed With CC
Tower-E 6 Completed With CC
Tower-E 7 Completed With CC
Tower-E 8 Completed With CC
Tower-E 9 Completed With CC
Tower-E 10 Completed With CC
Tower-E 11 Completed With CC
Tower-E 12 Completed With CC
Tower-E 13 Completed With CC
Tower-E 14 Completed With CC
Tower-E 15 Completed With CC
Tower-E 16 Completed With CC
Tower-E 17 Completed With CC
Tower-E 18 Completed With CC
Tower-E 19 Completed With CC
Tower-E 20 Completed With CC
Tower-E 21 Completed With CC
Tower-E 22 Completed With CC
Tower-E 23 Completed With CC
Tower-E 24 Completed With CC
Tower-E 25 Completed With CC
Tower-E 26 Completed With CC
Tower-E 27 Completed With CC
Tower-E 28 Completed With CC
Tower-E 29 Completed With CC
Tower-E 30 Completed With CC
Tower-F 1 Completed With CC
Tower-F 2 Completed With CC
Tower-F 3 Completed With CC
Tower-F 4 Completed With CC
Tower-F 6 Completed With CC
Tower-F 7 Completed With CC
Tower-F 8 Completed With CC
Tower-F 9 Completed With CC
Tower-F 10 Completed With CC
Tower-F 11 Completed With CC
Tower-F 12 Completed With CC
Tower-F 13 Completed With CC
Tower-F 14 Completed With CC
Tower-F 15 Completed With CC
Tower-F 16 Completed With CC
Tower-F 17 Completed With CC
Tower-F 19 Completed With CC
Tower-F 20 Completed With CC
Tower-F 21 Completed With CC
Tower-F 22 Completed With CC
Tower-F 23 Completed With CC
Tower-F 24 Completed With CC
Tower-F 25 Completed With CC
Tower-F 26 Completed With CC
Tower-F 27 Completed With CC
Tower-F 28 Completed With CC
Tower-F 29 Completed With CC
Tower-F 30 Completed With CC
Tower-G_residential 2 Under Construction
Tower-G_residential 3 Under Construction
Tower-G_residential 4 Under Construction
Tower-G_residential 5 Under Construction
Tower-G_residential 6 Under Construction
Tower-G_residential 7 Under Construction
Tower-G_residential 8 Under Construction
Tower-G_residential 9 Under Construction
Tower-G_residential 10 Under Construction
Tower-G_residential 11 Under Construction
Tower-G_residential 12 Under Construction
Tower-G_residential 13 Under Construction
Tower-G_residential 14 Under Construction
Tower-G_residential 15 Under Construction
Tower-G_residential 16 Under Construction
Tower-G_residential 17 Under Construction
Tower-G_residential 18 Under Construction
Tower-G_residential 19 Under Construction
Tower-G_residential 20 Under Construction
Tower-G_residential 21 Under Construction
Tower-G_residential 22 Under Construction
Tower-G_residential 23 Under Construction
Tower-G_residential 24 Under Construction
Tower-G_residential 25 Under Construction
Tower-G_commercial 1 Under Construction
Tower-G_commercial 2 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Infra
2 33KV ELECTRICAL RECEIVING STATION

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC EXTERNAL COMMON AREA
2 Completed With CC COMMON LOBBY AREA OF TOWER- E AND F

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 20-03-2019 31-03-2019 31-03-2019 none
Such other approvals as may be required and obtained for the project 05-05-2018 31-08-2018 24-08-2018 Partial Occupancy Certificate for Tower-A, B, C, D, CH, TH, Club, Amenity, Part Basement
Height clearance from Airport Authority of India (if any) 05-06-2016 16-06-2016 16-06-2016 revalidated
Consent to Establish and Operate 29-10-2018 27-11-2018 27-11-2018
Environmental Clearance 12-04-2018 16-07-2018 16-07-2018
Fire NOC 22-06-2016 21-09-2016 21-09-2016
Permission from Water and Sewerage department 01-10-2013 18-10-2013 18-10-2013