New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

MEENA FORTUNA

Project Status as on Quarter ending 31-12-2024
Updated as on 23-01-2025

Booking Status

  • Residential Apartments Booked
    172

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    159

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block A - 1st to 4th Floor 1 Completed With CC
Block A - 1st to 4th Floor 2 Completed With CC
Block A - 1st to 4th Floor 3 Completed With CC
Block A - 1st to 4th Floor 4 Completed With CC
Block B -1st to 4th Floor 1 Completed With CC
Block B -1st to 4th Floor 2 Completed With CC
Block B -1st to 4th Floor 3 Completed With CC
Block B -1st to 4th Floor 4 Completed With CC
Block C - 1st to 4th Floor 1 Completed With CC
Block C - 1st to 4th Floor 2 Completed With CC
Block C - 1st to 4th Floor 3 Completed With CC
Block C - 1st to 4th Floor 4 Completed With CC
Block D - 1st to 4th Floor 1 Completed With CC
Block D - 1st to 4th Floor 2 Completed With CC
Block D - 1st to 4th Floor 3 Completed With CC
Block D - 1st to 4th Floor 4 Completed With CC
Block E - 1st to 4th Floor 1 Completed With CC
Block E - 1st to 4th Floor 2 Completed With CC
Block E - 1st to 4th Floor 3 Completed With CC
Block E - 1st to 4th Floor 4 Completed With CC
Block F - 1st to 4th Floor 1 Completed With CC
Block F - 1st to 4th Floor 2 Completed With CC
Block F - 1st to 4th Floor 3 Completed With CC
Block F - 1st to 4th Floor 4 Completed With CC
Block G - 1st to 4th Floor 1 Completed With CC
Block G - 1st to 4th Floor 2 Completed With CC
Block G - 1st to 4th Floor 3 Completed With CC
Block G - 1st to 4th Floor 4 Completed With CC
Block H - 1st to 4th Floor 1 Completed With CC
Block H - 1st to 4th Floor 2 Completed With CC
Block H - 1st to 4th Floor 3 Completed With CC
Block H - 1st to 4th Floor 4 Completed With CC
Block I - 1st to 4th Floor 1 Completed With CC
Block I - 1st to 4th Floor 2 Completed With CC
Block I - 1st to 4th Floor 3 Completed With CC
Block I - 1st to 4th Floor 4 Completed With CC
Block J - 1st to 4th Floor 1 Completed With CC
Block J - 1st to 4th Floor 2 Completed With CC
Block J - 1st to 4th Floor 3 Completed With CC
Block J - 1st to 4th Floor 4 Completed With CC
Block K - 1st to 4th Floor 1 Completed With CC
Block K - 1st to 4th Floor 2 Completed With CC
Block K - 1st to 4th Floor 3 Completed With CC
Block K - 1st to 4th Floor 4 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Entrance
2 Completed With CC Meena Fortuna Entrance In & Out
3 Completed With CC Lobby
4 Completed With CC Lift
5 Completed With CC Roof
6 Completed With CC Project View
7 Completed With CC Game Room
8 Completed With CC Meena Fortuna GYM Room

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download