WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

EMPERADOR

Project Status as on Quarter ending 30-09-2020
Updated as on 01-12-2020

Booking Status

  • Commercial Unit Booked
    4

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    4

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 PILING COMPLETION WORK -1

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction PILING WORK -1
2 Under Construction PILING WORK IN PROGRESS

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download