WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    The last date for all the pending quarterly project updates has been extended till 30.04.2025,please upload all the pending quarterly updates within 30.04.2025 to avoid penalty.

ORCHARD PH2B AT GODREJ SE7EN

Project Status as on Quarter ending 31-03-2025
Updated as on 24-03-2025

Booking Status

  • Residential Apartments Booked
    508

  • Commercial Unit Booked
    11

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    291

  • Mechanical Parking Booked
    224

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 certificate
2 project site
3 project site
4 Architect Certificate

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started certificate
2 Not Started Architect certificate
3 Under Construction site photograph

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Consent to Establish and Operate 17-10-2023 17-11-2023 30-11-2023 CONSENT TO ESTABLISH
Environmental Clearance 16-01-2023 31-07-2024 16-10-2023 environmental clearance certificate
Environmental Clearance 29-08-2022 06-04-2023 16-10-2023 Environment clearance certificate