WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

SIDDHA SUBURBIA- BUNGALOW PHASE III

Project Status as on Quarter ending 30-09-2024
Updated as on 19-10-2024

Booking Status

  • Residential Apartments Booked
    43

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block-01 1 Under Construction
Block - 02 1 Under Construction
Block - 08 1 Under Construction
Block-09 1 Under Construction
Block - 10 1 Under Construction
Block - 11 1 Under Construction
Block - 12 1 Under Construction
Block - 13 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities
2 Emergency Evacuations
3 Internal Road/Carriage Way

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Club
2 Not Started Water Filteration Plant
3 Not Started Power Backup
4 Not Started Stairs
5 Not Started Lobby
6 Not Started Roof
7 Under Construction Septic Tank
8 Under Construction Under-Ground Water Reservoir
9 Not Started Overhead Tank
10 Under Construction Rain Water Harvesting Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download