Project Status as on Quarter ending 30-06-2024
Updated as on 17-07-2024

Booking Status

  • Commercial Unit Booked
    1

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Not Started
1 3 Not Started
1 4 Not Started
1 5 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities
2 Emergency Evacuations
3 Water Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Stairs
2 Not Started Lift
3 Not Started Lobby
4 Not Started Overhead Tank
5 Not Started Under-Ground Water Reservoir
6 Not Started Septic Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download