WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

PURTI AQUA 2

Project Status as on Quarter ending 31-03-2021
Updated as on 02-08-2021

Booking Status

  • Residential Apartments Booked
    96

  • Basement Parking Booked
    65

  • Covered Car Parking Booked
    15

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BREEZE 6 Under Construction
MIST 6 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction GROUND AREA COMMON SPACE

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 05-03-2021 05-04-2021 10-05-2021