WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Radhe Shyam Apartment Phase I

Project Status as on Quarter ending 30-09-2024
Updated as on 04-10-2024

Booking Status

  • Residential Apartments Booked
    15

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    9

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK- 1st to 7th Floor - Residential 1 Under Construction
BLOCK- 1st to 7th Floor - Residential 2 Under Construction
BLOCK- 1st to 7th Floor - Residential 3 Under Construction
BLOCK- 1st to 7th Floor - Residential 4 Under Construction
BLOCK- 1st to 7th Floor - Residential 5 Under Construction
BLOCK- 1st to 7th Floor - Residential 6 Under Construction
BLOCK- 1st to 7th Floor - Residential 7 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Under Construction Stairs
3 Not Started Lift
4 Not Started Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download