WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

SBM Upohar

Project Status as on Quarter ending 31-12-2023
Updated as on 28-02-2025

Booking Status

  • Residential Apartments Booked
    3

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    4

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed Without CC
1 2 Completed Without CC
1 3 Completed Without CC
1 4 Completed Without CC
2 1 Completed Without CC
2 2 Completed Without CC
2 3 Completed Without CC
2 4 Completed Without CC
4 1 Completed Without CC
4 2 Completed Without CC
4 3 Completed Without CC
4 4 Completed Without CC
6 1 Completed Without CC
6 2 Completed Without CC
6 3 Completed Without CC
6 4 Under Construction
7 1 Completed Without CC
7 2 Under Construction
7 3 Under Construction
7 4 Under Construction
8 1 Under Construction
8 2 Under Construction
8 3 Under Construction
8 4 Not Started
9 1 Under Construction
9 2 Under Construction
9 3 Under Construction
9 4 Not Started
10 1 Under Construction
10 2 Under Construction
10 3 Under Construction
10 4 Not Started
11 1 Under Construction
11 2 Under Construction
11 3 Under Construction
11 4 Not Started
12 1 Under Construction
12 2 Under Construction
12 3 Not Started
12 4 Not Started
13 1 Under Construction
13 2 Under Construction
13 3 Not Started
13 4 Not Started
14 1 Under Construction
14 2 Under Construction
14 3 Not Started
14 4 Not Started
15 1 Under Construction
15 2 Under Construction
15 3 Not Started
15 4 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download